NamPower charges ahead with grid plan
NamPower says it is rolling out a multibillion-dollar transmission expansion programme aimed at strengthening Namibia’s electricity network and meeting growing demand in different regions. The announcement was made at Swakopmund on Sunday during the inauguration of the Sekelduin Substation. The Sekelduin Substation was built between July 2021 and March 2023 and was officially inaugurated in […] The post NamPower charges ahead with grid plan appeared first on The Namibian .

NamPower says it is rolling out a multibillion-dollar transmission expansion programme aimed at strengthening Namibia’s electricity network and meeting growing demand in different regions.
The announcement was made at Swakopmund on Sunday during the inauguration of the Sekelduin Substation.

The Sekelduin Substation was built between July 2021 and March 2023 and was officially inaugurated in June. The project cost N$394 million.
Namibia Power Corporation (NamPower) managing director Simson Haulofu says the project is part of efforts to strengthen the national transmission system.