Kavango West office park at 99% completion
Lylie Joel NKURENKURU– The Kavango West Regional Council’s (KWRC) office park has reached 99% completion, with commissioning pending amid funding delays. According to KWRC Chief Development Planner Petrus Hamutenya in an interview with Nampa on Wednesday, N$181 065 050.47 of the N$190 215 587.90 contract has been spent since the commencement of the project on... The post Kavango West office park at 99% completion appeared first on New Era .

Lylie Joel

NKURENKURU– The Kavango West Regional Council’s (KWRC) office park has reached 99% completion, with commissioning pending amid funding delays. According to KWRC Chief Development Planner Petrus Hamutenya in an interview with Nampa on Wednesday, N$181 065 050.47 of the N$190 215 587.90 contract has been spent since the commencement of the project on 23 August 2021.