NamPower rolls out N$4-billion transmission network
NamPower says it is rolling out a multibillion-dollar transmission expansion programme aimed at strengthening Namibia’s electricity network and meeting growing demand in different regions. The announcement was made on Sunday at Swakopmund during the inauguration of a new electricity substation at Sekelduin. The Sekelduin Substation was built between July 2021 and March 2023 and was […] The post NamPower rolls out N$4-billion transmission network appeared first on The Namibian .

NamPower says it is rolling out a multibillion-dollar transmission expansion programme aimed at strengthening Namibia’s electricity network and meeting growing demand in different regions.

The announcement was made on Sunday at Swakopmund during the inauguration of a new electricity substation at Sekelduin.
The Sekelduin Substation was built between July 2021 and March 2023 and was officially inaugurated this month. The project cost N$394 million.